Catchwords:
BUILDING AND CONSTRUCTION – residential building contract – builder issues payment claim under Building and Construction Industry Security of Payment Act 1999 (NSW) for works at lock up stage – builder proceeds to adjudication and registers adjudication certificate as a judgment – where owners commence proceedings following dispute about termination of the contract – where primary judge found that works had not reached lock up stage and builder not contractually entitled to payment for works the subject of the claim – where primary judge found that owners validly terminated the contract and entitled to damages – application of s 32 Building and Construction Industry Security of Payment Act 1999 (NSW)